Asociația Proprietarilor
din Strop de Cersat Grid · comuna Pârâu · Brașov

The project

Two sections, two different problems

One is the road you take to reach Grid. The other is the network inside the area. They are handled separately, with separate procedures — and it matters not to mix them, because they are funded differently.

Access road

Grid → crossroads

A dirt-and-gravel road climbing from the village towards the development. The critical sections are the wet areas and the narrow forest stretches, where the bank needs embankments. In 2025, 2–2.5 km were graveled, stone over geotextile, compacted — that stretch is in good shape.

Length
4,85–5 km
Elevation gain
≈ 130 m
Average slope
2,7% (sectors >7%)
Gravelled 2025
2–2.5 km, good condition
Wet zones
7–8, over 3 m
Permit needed
ABA Olt – SGA Brașov
Public domain

The largest plot

CF 101549 (52,920 sqm) is the largest plot among the interior roads — about 48% of the network — already in the commune’s public domain (HCL 66/2025) and classified as a road of local interest (communal road) by HCL 53. What remains is the category change at OCPI, from ‘construction yards’ to ‘road’, and the inventory update. The rest of the plots follow, road by road, on ‘Strategy’.

Land title
CF 101549
Area
52.920 mp
Decision
HCL 53 / 06.07.2026
Category
communal road
Next step
Prefecture review

Access road profile

Grid → crossroads, by elevation

The nearly 5 km climb from 475 m to 565 m, with a dip in the middle. The marked stretch is the steepest — between km 0.75 and km 1.10, slope over 8% — where earthworks matter most. Data: EU-DEM elevation model, 25 m.

Ground elevation (EU-DEM 25 m)Slope over 8% zone
Profile: km 0 at 475 m, climbing to 554 m at km 2, descending to 523 m at km 3.3, climbing to 568 m at km 4.25, ending at 565 m at km 5.25.

On site

Road works progress

How much of each segment is done and how much of the cost is covered by contributions. Detailed amounts are in the members area.

Total covered
0%

Sector 1 · not a priority (passable)

Planned
km 0,68 – 1,13 · 450 mPlanned

Review + topping up a 5 cm layer of 0-31 stone

0% covered

Sector 2

Planned
Segment 1 · km 1,13 – 1,33 · 200 mPlanned

3 m road grading + dug ditches

0% covered

Segment 2 · km 1,33 – 1,53 · 200 mPlanned

3 m road grading + dug ditches

0% covered

Segment 3 · km 1,53 – 1,63 · 200 mPlanned

3 m road grading + dug ditches

0% covered

Sector 3

Planned
km 2,070 · —Planned

Replace Ø300 corrugated pipe (6 m) + rebuild culvert

0% covered

Sector 4

Planned
km după 2,070 · 50 mPlanned

3 m road grading + dug ditches (wet section)

0% covered

Sector 5

Planned
km 2,820 · 150 mPlanned

Review + 5 cm of 0-31 stone + ditch

0% covered

Sector 6

Planned
km 2,940 · —Planned

Culvert desilting + rainwater ditch extension

0% covered

Sector 7

Planned
km 3,04 – 3,14 · 100 mPlanned

Review + stone top-up on the steep ramp

0% covered

Sector 8

Planned
km 3,14 – 3,29 · 150 mPlanned

3 m road grading + ditches

0% covered

Sector 9

Planned
km 3,30 – 3,55 · 250 mPlanned

Review + install 50 m of capped concrete channel (Symmetrica)

0% covered

A member? The cost of each segment and the estimate are in Members.

Where we are

The administrative path

The path below follows CF 101549 — the most advanced road plot, already classified as a communal road by HCL 53. The other five road plots are further back, at the stage of HCL proposals to the town hall. See where each stands on Strategy.

06.07.2026Decision 53 adopted9 of 11 presentLegality reviewBrașov PrefecturenowLand registry · category changetown hall submits to OCPIupcomingAdded to inventorypossibly another council decisionupcomingFeasibility studyquotes in progressExecution
  1. 06.07.2026Decision 53 adopted9 of 11 present
  2. Legality reviewBrașov Prefecture
  3. nowLand registry · category changetown hall submits to OCPI
  4. upcomingAdded to inventorypossibly another council decision
  5. upcomingFeasibility studyquotes in progress
  6. Execution

The step-by-step plan, road by road →Search the plots in the Land registry →

A member? The legal status of each property and the documentation costs are in Members.